The Naos project began with a phone call which my person, Allan Rojas, answered on December 9, 2019, the call went to the ZEBOL headquarters, and I had the joy of being able to assist and help you.
A 78% reduction in the loading time of the boom spray was made, from 36 or 38 minutes to 6 to 8 minutes.
The equipment was operated under different circumstances or eventualities, carrying out all the performance tests of the system and others and everything was excellent.
A reduction in power consumption was realized for the application by going from using a 100 hp compressor to drive 8 pumps to consuming less than 4hp altogether for the 8 recommended pumps.
Currently the system has been in operation for several months and everything has been impeccable, from an installation topic to a technical equipment selection topic.
Our team is ready to talk about your project, contact us now.